The most detailed construction standards and plans for cleanrooms

(i) partition wall works
1. The loading and unloading of partition materials should avoid scratches, distortion, and impacts on the surface, and avoid open-air loading and unloading of interior materials (especially rock wool colored steel plate and mineral wool board) in case of rain.
2. Before installation of the metal wall panel, routing should be carried out in accordance with the construction drawing, and consideration should be given to the routing of the door panel. The line should adopt infrared level to ensure accuracy. Formal construction, the plate should be screened, the surface will have scratches, pits, larger diagonal deviation of the plate to adjust to not affect the appearance and function of the parts of the use.
3. Wall corners should be vertically connected, to prevent the wall plate tilt distortion, wall plate verticality deviation shall not be greater than 0.15% (ceiling 2600mm as an example, verticality deviation shall not be greater than 4mm).
4. The wall plate installation should be vertical, flat, correctly positioned, with the ceiling plate and the relevant wall plate at the intersection, should take anti-cracking measures; its joints should be sealed. The clean area of the pharmaceutical clean room, between the wall and wall, wall and ground, wall and top need to use aluminum alloy arc transition (inner arc, outer arc), the arc between the wall and top should be fixed and reliable, to avoid falling off due to the ceiling on people. The bracket within the arc should be full of cloth. Non-clean area without arc transition (according to the actual situation for adjustment, such as changing shoes area general practice with clean area), wall and ground not arc.
5. Wall panel seam gap should be consistent, each panel seam gap error is not greater than 0.5mm, the diagonal deviation of the larger panel should be adjusted to use.
6. Wall panels on the electrical junction boxes, control panels and pipelines through a variety of holes, should be the correct location, neat edges, tight, clean, no dust production, and should be non-combustible or flame-retardant materials to seal. Installation of doors and windows should be left openings in line with design requirements, and should be flat, tight, clean, no dust production.
7. The wall plate installation of the allowable deviation and inspection methods, should comply with the requirements of the following table.
8, doors and windows surface should not be dusty, not moldy, not absorbing pollutants, easy to clean and disinfection, smooth, smooth, doors and windows on the glass should be fixed type.
9. When the width of a single door is greater than 600mm, the door and door frame hinges should not be less than 3. Frame and the wall should be firmly connected, the surface should be sealed with sealant uniform seal.
10. Door and window notches diagonal length of the allowable deviation should be 3mm, door and window frame level of the allowable deviation should be 2mm.
11. Movable door shall not scrape the ground, the switch should be flexible. Doors and windows frame and the wall should be connected firmly. The gap between the window and door frames, secondary frame and the wall should be uniform, and shall not exceed 1mm. The gap should be filled with sealing material and sealant seal.
12. Doors and windows should be consistent color surface, no rust, no scratches and bruises. The glass sandwich space should be clean and the glass surface should be bright.
Allowable deviations and test methods of doors and windows installation should be in line with the provisions of the following table.
Cleanroom doors and windows of the allowable deviation and test methods of installation
13. The surface of the wall should be flat, smooth, consistent color, no rust, no scratches and bruises, the metal wall plate mask should be intact (before tearing the film). After the completion of the interior, the construction waste clean up, no other professional construction, before tearing the surface film.
14. After further cleaning, the ceiling and partition should be airtight. Sealant should be even, flat, smooth, slightly below the board surface, no interruptions, impurities.
(ii) ceiling project
1. Before the construction of the ceiling project, the following concealed works shall be inspected and handed over.
(1) `the installation project of all kinds of pipes, functional facilities and equipment in the suspended ceiling.
(2) installation of keels, booms and embedded parts, etc., including fire, corrosion, mildew and dust treatment.
(3) other concealed projects related to the suspended ceiling.
2. Before the installation of the keel, according to the design requirements for the net height of the room, the elevation of the hole and the ceiling pipeline, equipment and other support elevation, etc. To handle the process transfer procedures.
3. In the ceiling project of buried parts, reinforcing steel rod and shape steel rod should carry on antirust or anticorrosion treatment; when the ceiling upper part as static pressure box, buried parts and the floor or wall of the articulation place, should carry on sealing treatment. Support hanger should take dustproof processing.
4. The fixed and hanging parts of the ceiling, should be connected with the main structure. Shall not be connected with equipment bracket and pipeline bracket; ceiling hangings shall also not be used as pipeline hanger or equipment hanger.
5. Air filters, lamps, smoke detectors, loudspeakers and all kinds of pipeline through the ceiling at the hole around the hole should be flat, tight, clean, and blocked with non-combustible materials. The perimeter of the maintenance opening of the concealed project should be sealed with sealing gasket.
6. The ceiling elevation, size, arch, plate gap should comply with the design requirements. The gap between the board should be consistent, each gap between the board error shall not be greater than 0.5mm; and with sealant evenly sealed, do flat, smooth, slightly below the board, shall not have a break and impurities.
7. The material of the ceiling finish, varieties, specifications, etc., should comply with the design requirements, and the product performance for verification.
8. The spacing between the hanging rods should be bigger than 1.5m. The distance between the hanging rods and the main keel end should not be bigger than 300mm.
9. The installation of the boom, keel and decorative panel must be safe and firm.
10. The material, specification and connection mode of the boom, keel, should conform to the design requirements. The metal hanging rod, keel should carry on the surface anticorrosion treatment.
11. Ceiling finish surface should be clean, smooth, color and luster consistent, not have warp, crack and defect; and shall not have mildew, not produce dust.
12. Metal hanging rod, keel of the joint should be uniform, corner seam should match, the surface should be smooth, no warp, hammer mark.
13. The ceiling project installation of the allowable deviation and inspection method shall conform to the provisions of the following table.
Allowable deviation of ceiling project installation and inspection method
(iii) flooring works
1. Confirmation of grass-roots conditions shall be in accordance with the following requirements.
(1) the base should be solid and firm (above c25 concrete), no crusting, honeycomb, pitting, hollow drum, chalking, cracks and other phenomena.
(2) the concrete foundation should be dry for more than 28 days, and the ground floor should be waterproofed; during construction, the water content should be less than 8%, otherwise it may cause the epoxy flooring blisters to fall off.
(3) the surface is basically flat, no unevenness, honeycomb pitting surface, cement lumps and other phenomena, it is recommended that the construction of concrete with laser leveling and concrete power trowel machine light, using power trowel smoothing, can improve the construction efficiency and precision, can also use another kind of ride on power trowel for smoothing concrete floor. Ensure that the flatness of two meters leaner on the ground and the ground clearance is less than 5mm.
(4) concrete floors without oil, wax, other paints, latex paint and other pollution.
(5) for the old ground for paint, resin and pvc floor removal, the surface of the grass-roots level should be polished clean and leveled with putty or cement repair.
(6) when the grass-roots level is tile, terrazzo, the height difference between adjacent plates should not be more than 1.0mm, there should be no loose plates, cracks and other phenomena.
2. Epoxy flooring shall meet the following requirements
(1) the thickness and properties of the coating shall meet the design requirements.
(2) the top coat shall be applied after the bond layer has been dried.
(3) the ambient temperature of the surface layer construction shall be controlled at 5~35℃.
(4) the construction of the surface layer should be completed in one time. When the construction is done in several times, it should be done with few joints and set in the concealed place. The joints shall be flat and smooth, no color separation and no bottom exposure.
(5) the surface shall be free of cracks, blisters, delamination, pitting, etc..
(6) the surface resistance of the anti-static ground should meet the design requirements.
(4) elevated floor
1. The elevated floor and its supporting structure should conform to the design and load-bearing requirements. Before installation, it should check the factory certificate and review the load inspection report, and each specification should have the corresponding inspection report.
2. The building ground where the elevated floor is laid shall meet the following requirements.
(1) ground elevations shall conform to design requirements.
(2) the surface layer of the ground should be smooth, smooth, dust-free, with a moisture content of not more than 8 per cent, and painted according to the design requirements.
3. The surface layer and supporting parts of the elevated floor should be smooth and solid, and have such properties as wear-resisting, mildew-proof, moisture-proof, flame retardant or non-flammable, pollution-resistant, aging-resistant, static conductivity, acid and alkali-resistant.
4. To have anti-static requirements of the elevated floor, should verify the product factory certification, certification and anti-static performance test report before installation.
5. For the elevated floor with ventilation requirements, the aperture rate and distribution of aperture, aperture or side length on the surface layer should meet the design requirements.
6. The connection or bonding between the support pole of the elevated floor and the building ground should be solid and reliable. The connection of metal components underneath the support pole should meet the design requirements, and the exposed wire buckle of the fixed bolt should not be less than 3 buckles.
7. The allowable deviation of the elevated floor surface layer laying shall conform to the provisions of the following table.
8. The elevated floor should be carefully aligned before construction, and the elevation datum point and the installation position and height of the floor block should be correctly selected.
9. There should be no swing, no sound and good firmness after the installation of the elevated floor. The surface layer of the elevated floor should be flat and clean, and the joints of plates and pieces should be flat and straight.
10. The installation of the plate at the edge and corner position of the elevated floor should be set and mended after cutting according to the actual situation, with adjustable support and crossbar set up, and the soft dust-producing material should be used to fill in the joints between the cutting edge and the wall.